City of Monroe's 2022 Overlay Award
3-P-822(008)-1
3-P-822(008)-1
2022 Overlay Award
Multiple Locations
FY 2024 Arterial Preservation Program
Current Phase : Bid Authorization
Total TIB Funding : $798,445
County: Snohomish | Legislative District: 39 | Project Length: 0.98 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | MONROE |
Funding Year | 2024 |
Program | APP |
Current Phase | Bid Authorization |
Legislative District | 39 |
Congressional District | 1 |
Federal Route Number | 2633 |
Project Length | 0.98 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | Scott Peterson |
Contact Email | speterson@monroewa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 01/26/2023 |
Bid Auth. Approval | 04/02/2024 | 03/28/2024 |
Construction Approval | 04/18/2024 | |
Project Closeout | 09/30/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 92,128 | 131,612 |
Right of Way | 0 | 0 |
Total Design | 92,128 | 131,612 |
Construction Engineering | 92,128 | 131,612 |
Construction Contract | 614,189 | 877,413 |
Other Construction | 0 | 0 |
Total Construction | 706,317 | 1,009,025 |
Total TIB Funding | 798,445 | 1,140,637 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MONROE | 342,192 | 30.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 342,192 | 30.0% |
Project Description
This project grinds and provides a 2-inch overlay of the following segments Blueberry Lane - 182nd Ave to N Kelsey St NB Freylands Boulevard - Wales St SE to Tye St SE City will cover the costs of the upgrade of 16 ADA ramps
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |