The pavement condition rating of this segment of Hinkleman Road is 28.
Projects — TIB Project Information
TIB Project Information
City of Buckley's Hinkleman Road Rehabilitation
3-P-808(001)-1
3-P-808(001)-1
Hinkleman Road Rehabilitation
Hinkleman Ext to 28307 Hinkleman Rd
FY 2023 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $278,472
County: Pierce | Legislative District: 31 | Project Length: 0.36 | TIB Engineer: Greg Armstrong | Last Payment Date: 02/23/2023
Project Information
Lead Agency | BUCKLEY |
Funding Year | 2023 |
Program | APP |
Current Phase | Construction |
Legislative District | 31 |
Congressional District | 8 |
Federal Route Number | 3202 |
Project Length | 0.36 mi. |
ADT | 250 |
Functional Class | Collector |
Type of Work | Reconstruction |
Project Contact | Chris Banks |
Contact Email | cbanks@cityofbuckley.com |
TIB Engineer | Greg Armstrong |
Last Payment Date | 02/23/2023 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2022 | 12/02/2021 |
Bid Auth. Approval | 05/01/2023 | 04/19/2023 |
Construction Approval | 06/13/2023 | 06/20/2023 |
Project Closeout | 06/30/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 31,875 | 37,500 |
Right of Way | 0 | 0 |
Total Design | 31,875 | 37,500 |
Construction Engineering | 31,875 | 37,500 |
Construction Contract | 214,722 | 258,585 |
Other Construction | 0 | 0 |
Total Construction | 246,597 | 296,085 |
Total TIB Funding | 278,472 | 333,585 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
BUCKLEY | 55,113 | 16.5% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 55,113 | 16.5% |
Project Description
Full depth reclamation with a 2-inch overlay
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |