Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Prosser's Wine Country Road Overlay

3-E-923(003)-1

3-E-923(003)-1
Wine Country Road Overlay

Merlot Dr to Yakima River Bridge

FY 2023 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $454,328

County: Benton   |   Legislative District: 16   |   Project Length: 0.90   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 01/31/2023

Project Information

Lead Agency PROSSER
Funding Year 2023
Program APP
Current Phase Audit
Legislative District 16
Congressional District 4
Federal Route Number 3733
Project Length 0.90 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Marty Groom
Contact Email mgroom@ci.prosser.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date 01/31/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2022 12/17/2021
Bid Auth. Approval 04/15/2022 04/25/2022
Construction Approval 05/15/2022 05/25/2022
Project Closeout 11/28/2022 01/27/2023
Audit Date   01/31/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 42,750 47,500
Right of Way 0 0
Total Design 42,750 47,500
     
Construction Engineering 42,750 47,499
Construction Contract 329,490 430,474
Other Construction 0 0
Total Construction 372,240 477,973
     
Funding Increase 62,248  
Funding Surplus - 22,910  
Total TIB Funding 454,328 525,473

Local Funding Partners

Funding Amount Percent
PROSSER 71,145 13.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 71,145 13.5%

Project Description

Grind and overlay 2-inch depth.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.