Projects — TIB Project Information
TIB Project Information
City of Ellensburg's Main Street Overlay
3-E-175(004)-1
3-E-175(004)-1
Main Street Overlay
3rd Ave to University Way
FY 2024 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $262,693
County: Kittitas | Legislative District: 13 | Project Length: 0.37 | TIB Engineer: Jonathan Heusman | Last Payment Date: 01/31/2024
Project Information
Lead Agency | ELLENSBURG |
Funding Year | 2024 |
Program | APP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 8 |
Federal Route Number | 6949 |
Project Length | 0.37 mi. |
ADT | 0 |
Functional Class | Principal |
Type of Work | Resurfacing |
Project Contact | Derek Mayo |
Contact Email | mayod@ci.ellensburg.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 01/31/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 01/09/2023 |
Bid Auth. Approval | 04/15/2023 | 05/01/2023 |
Construction Approval | 05/31/2023 | 05/23/2023 |
Project Closeout | 11/30/2023 | 01/18/2024 |
Audit Date | 01/31/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 9,865 | 15,755 |
Right of Way | 0 | 0 |
Total Design | 9,865 | 15,755 |
Construction Engineering | 24,334 | 25,794 |
Construction Contract | 365,801 | 357,582 |
Other Construction | 0 | 294 |
Total Construction | 390,135 | 383,670 |
Funding Increase | 2,714 | |
Funding Surplus | - 140,021 | |
Total TIB Funding | 262,693 | 399,425 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ELLENSBURG | 136,732 | 34.2% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 136,732 | 34.2% |
Project Description
Pavement distress appears to be surface degradation only. Use 2 in. HMA grind and overlay to preserve pavement, and fill-in missing segment between two other recent overlay projects. City to pay for curb ramp and sidewalk replacement. Main Street - 3rd Ave to University Way
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |