The pavement condition rating of N 62nd Avenue - Van Giesen St to Harrington Rd 50
Projects — TIB Project Information
TIB Project Information
City of West Richland's N 62nd Avenue Overlay
3-E-172(005)-1
3-E-172(005)-1
N 62nd Avenue Overlay
Van Giesen St to Harrington Rd
FY 2023 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $177,376
County: Benton | Legislative District: 8 | Project Length: 0.47 | TIB Engineer: Jonathan Heusman | Last Payment Date: 02/13/2024
Project Information
Lead Agency | WEST RICHLAND |
Funding Year | 2023 |
Program | APP |
Current Phase | Audit |
Legislative District | 8 |
Congressional District | 4 |
Federal Route Number | 3452 |
Project Length | 0.47 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Roscoe Slade |
Contact Email | roscoe@westrichland.org |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 02/13/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2022 | 12/15/2021 |
Bid Auth. Approval | 04/15/2023 | 02/09/2023 |
Construction Approval | 02/28/2023 | 03/07/2023 |
Project Closeout | 02/28/2024 | 02/08/2024 |
Audit Date | 02/13/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 11,659 | 15,206 |
Right of Way | 0 | 0 |
Total Design | 11,659 | 15,206 |
Construction Engineering | 11,659 | 24,537 |
Construction Contract | 173,270 | 168,933 |
Other Construction | 0 | 0 |
Total Construction | 184,929 | 193,470 |
Funding Surplus | - 19,212 | |
Total TIB Funding | 177,376 | 208,676 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WEST RICHLAND | 31,300 | 15.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 31,300 | 15.0% |
Project Description
Project will taper grind the existing asphalt along the gutters and overlay with 2 inches of hot mix asphalt.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |