The pavement condition rating of Clay Street and 6th Street - 4th St to N 2nd St 59.
Projects — TIB Project Information
TIB Project Information
City of Cheney's 2021 Overlay
3-E-168(005)-1
3-E-168(005)-1
2021 Overlay
Multiple Locations
FY 2023 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $533,300
County: Spokane | Legislative District: 6 | Project Length: 0.29 | TIB Engineer: Andrew Beagle | Last Payment Date: 10/16/2023
Project Information
Lead Agency | CHENEY |
Funding Year | 2023 |
Program | APP |
Current Phase | Audit |
Legislative District | 6 |
Congressional District | 5 |
Federal Route Number | 7702 |
Project Length | 0.29 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Todd Ableman |
Contact Email | tableman@cityofcheney.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 10/16/2023 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2022 | 01/10/2022 |
Bid Auth. Approval | 01/31/2023 | 02/15/2023 |
Construction Approval | 02/28/2023 | 02/15/2023 |
Project Closeout | 09/30/2023 | 10/12/2023 |
Audit Date | 10/16/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 43,742 | 35,066 |
Right of Way | 0 | 0 |
Total Design | 43,742 | 35,066 |
Construction Engineering | 52,473 | 50,314 |
Construction Contract | 437,085 | 534,969 |
Other Construction | 0 | 0 |
Total Construction | 489,558 | 585,283 |
Total TIB Funding | 533,300 | 620,349 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CHENEY | 87,049 | 14.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 87,049 | 11.8% |
Project Description
Remove and replace non-compliant ADA ramps within the project limits remove areas of alligator cracking and provide new HMA patch seal all existing cracks, 1/4 and larger provide 7 wide taper grind along shoulders to maintain curb reveal grind as
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |