City of East Wenatchee's 2022 Overlay Award
3-E-161(004)-1
3-E-161(004)-1
2022 Overlay Award
McGee St SE to Grant Rd
FY 2024 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $402,239
County: Douglas | Legislative District: 12 | Project Length: 0.21 | TIB Engineer: Andrew Beagle | Last Payment Date: 08/31/2023
Project Information
Lead Agency | EAST WENATCHEE |
Funding Year | 2024 |
Program | APP |
Current Phase | Construction |
Legislative District | 12 |
Congressional District | 8 |
Federal Route Number | 5901 |
Project Length | 0.21 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Garren Melton |
Contact Email | gmelton@eastwenatcheewa.gov |
TIB Engineer | Andrew Beagle |
Last Payment Date | 08/31/2023 |
Cultural Resource Assessment | CRA & BER |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | 01/04/2024 | |
Predesign Approval | ||
Design Approval | 02/01/2023 | 02/13/2023 |
Bid Auth. Approval | 11/10/2023 | 01/08/2024 |
Construction Approval | 02/15/2024 | 02/20/2024 |
Project Closeout | 10/30/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 59,500 | 70,000 |
Right of Way | 0 | 0 |
Total Design | 59,500 | 70,000 |
Construction Engineering | 29,750 | 53,000 |
Construction Contract | 357,000 | 376,017 |
Other Construction | 0 | 0 |
Total Construction | 386,750 | 429,017 |
Funding Surplus | - 44,011 | |
Total TIB Funding | 402,239 | 499,017 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
EAST WENATCHEE | 47,078 | 9.4% |
WSDOT Funding | 0 | 0.0% |
East Wenatchee Water District | 49,700 | 10.0% |
Total Local Funding | 96,778 | 16.8% |
Project Description
Mill and fill, upgrade 5 ADA ramps. Water District steel main replacement companion project. Rock Island Road - Grant Rd to McGee St SE
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |