City of Stevenson's McEvoy Lane Overlay

2-W-974(003)-1

2-W-974(003)-1
McEvoy Lane Overlay

W End to E End

FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $47,444

County: Skamania   |   Legislative District: 14   |   Project Length: 0.16   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 12/14/2023

Project Information

Lead Agency STEVENSON
Funding Year 2024
Program SCPP
Current Phase Audit
Legislative District 14
Congressional District 3
Federal Route Number 9999
Project Length 0.16 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Carolyn Sourek
Contact Email carolyn@ci.stevenson.wa.us
TIB Engineer Chris Langhoff
Last Payment Date 12/14/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 01/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 01/30/2023
Bid Auth. Approval 04/15/2023 01/30/2023
Construction Approval 05/01/2023 01/30/2023
Project Closeout 10/30/2023 12/06/2023
Audit Date   12/14/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 74,146 49,941
Other Construction 0 0
Total Construction 74,146 49,941
     
Funding Surplus - 26,702  
Total TIB Funding 47,444 49,941

Local Funding Partners

Funding Amount Percent
STEVENSON 2,497 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 2,497 5.0%

Project Description

2 inch overlay McEnvoy Lane - W End to E End

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.