Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Kalama's 2022 Maintenance Project

2-W-953(005)-1

2-W-953(005)-1
2022 Maintenance Project

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $35,625

County: Cowlitz   |   Legislative District: 20   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 11/01/2023

Project Information

Lead Agency KALAMA
Funding Year 2024
Program SCPP
Current Phase Audit
Legislative District 20
Congressional District 3
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Kelly Rasmussen
Contact Email krasmussen@kalama.com
TIB Engineer Chris Langhoff
Last Payment Date 11/01/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/09/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 12/19/2022
Bid Auth. Approval 06/01/2023 12/19/2022
Construction Approval 06/01/2023 09/14/2023
Project Closeout 10/30/2023 09/21/2023
Audit Date   11/01/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 35,625 47,189
Other Construction 0 0
Total Construction 35,625 47,189
     
Total TIB Funding 35,625 47,189

Local Funding Partners

Funding Amount Percent
KALAMA 11,564 24.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 11,564 24.5%

Project Description

Crack seal

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments