TIB Project Information

City of Gold Bar's 2022 Overlay Award

2-P-819(006)-1

2-P-819(006)-1
2022 Overlay Award

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $278,450

County: Snohomish   |   Legislative District: 39   |   Project Length: 0.72   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 10/31/2023

Project Information

Lead Agency GOLD BAR
Funding Year 2024
Program SCPP
Current Phase Audit
Legislative District 39
Congressional District 1
Federal Route Number 9999
Project Length 0.72 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Rich Norris
Contact Email r.norris@cityofgoldbar.us
TIB Engineer Greg Armstrong
Last Payment Date 10/31/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 12/12/2022
Bid Auth. Approval 05/15/2023 04/11/2023
Construction Approval 05/10/2023 05/08/2023
Project Closeout 10/31/2023 10/19/2023
Audit Date   10/31/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 57,876 45,824
Right of Way 0 0
Total Design 57,876 45,824
     
Construction Engineering 28,938 21,693
Construction Contract 318,317 225,434
Other Construction 0 0
Total Construction 347,255 247,127
     
Funding Surplus - 126,681  
Total TIB Funding 278,450 292,951

Local Funding Partners

Funding Amount Percent
GOLD BAR 14,501 4.9%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 14,501 4.9%

Project Description

This project grinds and provides a 2-inch overlay of the follow segments 1st Avenue W from 1st St to Smeltzer Rd 415th Avenue SE from SR 2 to 419th Ave SE Dorman Road From SR 2 to BNSF Railroad Tracks

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.