 Projects — TIB Project Information

TIB Project Information

City of Mesa's 2022 Crack Seal

2-E-928(004)-1

2-E-928(004)-1
2022 Crack Seal

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $18,918

County: Franklin   |   Legislative District: 9   |   Project Length: 5.70   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 11/29/2023

Project Information

Lead Agency MESA
Funding Year 2024
Program SCPP
Current Phase Audit
Legislative District 9
Congressional District 4
Federal Route Number 9999
Project Length 5.70 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Alan Rainey
Contact Email alan@spinkeng.com
TIB Engineer Jonathan Heusman
Last Payment Date 11/29/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/12/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/30/2023 02/27/2023
Bid Auth. Approval 05/01/2023 06/21/2023
Construction Approval 08/31/2023 09/11/2023
Project Closeout 11/30/2023 11/17/2023
Audit Date   11/29/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 30,000 18,918
Other Construction 0 0
Total Construction 30,000 18,918
     
Funding Increase 3,252  
Funding Surplus - 14,334  
Total TIB Funding 18,918 18,918

Local Funding Partners

Funding Amount Percent
MESA 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

City wide crack seal of roads using small works roster.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.